Common Questions

I Have Received a Party Wall Notice – What Should I Do?

​

Receiving a Party Wall Notice from your neighbour can be a little worrying, particularly if you have never dealt with one before. You may be wondering why you have received it, whether you have to agree to the proposed building works, and what happens if something goes wrong.

​

The good news is that receiving a Party Wall Notice does not necessarily mean there is a problem. It is usually a normal part of the legal process when someone intends to carry out building works that may affect a neighbouring property.

​

The Party Wall etc. Act 1996 provides a framework that allows certain building works to proceed while protecting the interests of neighbouring property owners.

​

Let's look at what receiving a notice means and what you should do next.

​

​

Why have I received a Party Wall Notice?

​

You have probably received a notice because your neighbour is planning building works that fall within the Party Wall etc. Act 1996.

​

Common examples include:

​

  • A loft conversion involving structural alterations to a shared wall.

  • A rear or side extension requiring excavation close to your property.

  • Removing a chimney breast attached to a party wall.

  • Building a new wall along or astride the boundary.

  • Raising or altering an existing party wall.

  • ​

The person proposing the works is referred to as the Building Owner, while the neighbouring property owner receiving the notice is called the Adjoining Owner.

​

Receiving a notice does not mean your neighbour has done anything wrong. In fact, serving the appropriate notice is generally a sign that they are following the correct legal procedure.

​

​

Do I have to respond to the notice?

​

For most Party Wall Notices, you should respond in writing within 14 days.

​

If the notice relates to work on an existing party wall or certain excavations near your property, failing to respond within this period will normally result in a dispute being deemed to have arisen under the Act.

​

This does not mean you and your neighbour have fallen out. It is simply the legal process that allows surveyors to become involved and prepare a Party Wall Award where necessary.

​

There are different rules for notices concerning the construction of new walls along a boundary, so it is important to establish which type of notice you have received.

​

​

What are my options?

​

If you have received a notice relating to works to an existing party wall or adjoining excavation, there are generally three options available.

​

Option 1 – Consent to the proposed works

​

If you are comfortable with the proposals, you can provide your written consent.

​

This allows the works covered by the notice to proceed without the need for a Party Wall Award, subject to the applicable notice period or any valid agreement to an earlier start.

​

Consenting does not mean you give up your rights under the Act or that your neighbour is free to damage your property.

​

However, without an Award, there will not be the same formal arrangements setting out how the notifiable works are to be undertaken.

​

For relatively straightforward works, particularly where there is a good relationship between neighbours, consent may be a perfectly reasonable option.

​

Our advice: Before consenting, make sure you understand what your neighbour intends to do and consider whether a photographic Schedule of Condition would be sensible.

​

​

Option 2 – Dissent and appoint an Agreed Surveyor

​

If you would prefer the protection of a formal Party Wall Award, you can dissent from the notice.

​

You and your neighbour may then jointly appoint one independent surveyor, known as an Agreed Surveyor.

​

Despite the name, an Agreed Surveyor does not act on behalf of either owner. Their responsibility is to act impartially and consider the interests of both parties within the provisions of the Act.

​

The Agreed Surveyor will review the relevant proposals, consider appropriate safeguards and prepare a Party Wall Award.

​

This can be a practical and cost-effective arrangement where both owners are comfortable appointing the same professional.

​

Option 3 – Dissent and appoint your own surveyor

​

You can instead appoint your own Party Wall Surveyor, while your neighbour appoints a separate surveyor.

​

The two surveyors will then consider the proposed works and agree the terms of a Party Wall Award.

​

This arrangement may be preferable where the proposed works are particularly complicated, there are concerns about the adjoining property, or you would simply feel more comfortable having a separately appointed surveyor.

​

Although you appoint the surveyor, they must still act impartially when exercising their statutory duties.

​

​

Will I have to pay for a Party Wall Surveyor?

​

This is one of the most common concerns we hear from Adjoining Owners.

​

In most straightforward cases, the Building Owner proposing the works will be responsible for the reasonable surveyors' fees associated with the Party Wall process.

​

However, this is not an automatic entitlement to appoint any surveyor at any cost.

​

The Act allows the surveyor or surveyors to determine the reasonable costs of resolving the dispute, taking account of the circumstances.

​

If you are considering appointing a surveyor, it is sensible to establish their fees and the likely arrangements for payment at the outset.

​

​

What is a Party Wall Award, and how does it protect me?

​

A Party Wall Award is a legally binding document prepared by the appointed surveyor or surveyors to resolve matters arising under the Act.

​

Depending on the nature of the proposed works, it may address:

​

  • The notifiable building works that are authorised.

  • How and when those works are to be carried out.

  • Measures to reduce the risk of unnecessary damage or inconvenience.

  • Temporary protection and access arrangements.

  • The responsibilities of the Building Owner.

  • Procedures for dealing with damage arising from the works.

​

A Schedule of Condition is also commonly prepared before construction begins. This records the existing condition of relevant parts of your property, usually through written notes and photographs.

​

Although a Schedule of Condition is not a statutory requirement for every Award, it provides a useful reference if concerns about damage arise later.

​

It is important to understand that an Award cannot guarantee that damage will never occur. Its purpose is to establish appropriate arrangements and provide a framework for dealing with matters arising under the Act.

​

​

Can I stop my neighbour from carrying out the works?

​

Generally, you cannot prevent your neighbour from exercising rights that the Party Wall etc. Act 1996 gives them simply because you do not want the work to proceed.

​

However, you are entitled to expect that the relevant statutory procedures are followed and that appropriate consideration is given to protecting your property.

​

A Party Wall Surveyor can consider matters such as construction methods, temporary protection, access and the manner in which the notifiable works are undertaken.

​

The Party Wall process is not a substitute for planning permission or Building Regulations approval, and it does not provide a general right to object to a neighbour's development.

​

​

What should I do before responding?

​

We would recommend taking a little time to understand the proposals before making your decision.

​

  1. Read the notice carefully. Check what work is proposed and when it is intended to begin.

  2. Ask to see the drawings. These may help you understand how the works could affect your property.

  3. Speak to your neighbour. A friendly conversation can often resolve initial concerns.

  4. Consider the condition of your property. Think about whether a photographic Schedule of Condition would be beneficial.

  5. Seek independent advice if you are unsure. A Party Wall Surveyor can explain the notice and help you decide which response is appropriate.

​

Remember that the 14-day response period is important for most notices, so avoid leaving matters until the last minute.

​

​

Do I need to appoint a Party Wall Surveyor?

​

Not necessarily.

​

If the works are straightforward, you understand what is proposed and you are comfortable consenting, there may be no need to appoint a surveyor.

​

On the other hand, where structural alterations, significant excavations or other potentially sensitive works are proposed, having a formal Party Wall Award may provide useful reassurance.

​

The important thing is to make an informed decision rather than feeling pressured into either consenting or dissenting.

​

Need help understanding your Party Wall Notice?

​

At Bexley Party Walls, we understand that receiving a formal notice about your neighbour's building works can raise questions.

​

We are happy to explain what the notice means, discuss the proposed works and help you understand your options under the Party Wall etc. Act 1996.

​

Whether you ultimately decide to consent, appoint an Agreed Surveyor or appoint your own surveyor, our aim is to help you make an informed decision.

​

If you have received a Party Wall Notice and would like some initial guidance, please contact Bexley Party Walls for a friendly, no-obligation discussion.

​

​

​

​

​

​

​